AssetWise CONNECT Edition Help

To Close the Issue Task on an EWN

After all work has completed EWN, it may be closed.
Follow these steps to close the Issue task on an Early Warning Notification:
  1. From the Contractor's Work Exchange Work in Progress page, select the EWN for which you want to close.
  2. Select the Attributes tab.
  3. In the Contractor's early warning notification section, describe the details of the notification.
  4. In the Clause 16.1 - The event could: box, select one or more phrases that best suit the cause of this notification such as Delay completion, Delay meeting a Key Date, or Increase the Contractor's cost, for example.
    Note: This field is required.
  5. Select the Severity Your options are Low, Medium, or High.
    Note: This field is required.
  6. Select whether a risk reduction meeting is required, and if Yes, then you must select a Risk reduction meeting date by clicking the calendar icon ( ), and selecting a date.
  7. Provide a description in the Close out commentary box.
  8. From the Work Task menu, select Complete. A task notification dialog appears, the task is added to the Project Manager's Work Exchange - Work in Progress folder, a snapshot is created, and users subscribed to the EWN automatically receive an email notification that the snapshot has been created.
  9. Select the Snapshots tab to view a list of snapshots that have been created for this EWN. Users that are subscribed to the EWN automatically receive an email notification that the snapshot has been created.
The workflow advances to the Assign Action step.